Gambro Health Care - Plumbing Main Replacement

 

  • Replace plumbing main servicing clean room / manufacturing areas.
  • Work disrupted main service corridor where finished product was moved to warehouse
  • Cleanliness issues were paramount as clean room shutdown would have cost Gambro $1million per day.
  • Excavation and backfill completed over the week between Christmas and New Years and had to be complete and ready for resumption of operations on January 3rd
  • Remaining work completed with facility remaining operational
  • Project completed on-time and roughly $30,000 under budget

 